Line 1: Line 1:
 
=Agenda & Priority List=
 
=Agenda & Priority List=
  
SOA Design Timeline:<br>
 
- 2.17.2012  Concepts for SOA spin due <br>
 
- 3.02.2012  Fleshed-out designs for mask inclusion <br>
 
- 3.16.2012  Designs ready for review (i.e. gds files) <br>
 
- 3.30.2012  Mask tapeout deadline <br>
 
- 4.15.2012  Processing begins <br> <br>
 
  
 
Back to [[Process Hybrid Silicon]].
 
Back to [[Process Hybrid Silicon]].

Revision as of 15:36, 13 January 2012

Agenda & Priority List

Back to Process Hybrid Silicon.

Priority list

  • Process development:
    • Etch-back module (Jock, Jared)
    • Need to converge on process follower (Excel?)
  • III/V epi design
    • Finalize design
    • Order epi
  • III/V SOA design
  • III/V SOA mask design (UCSB-E-Phi-dev-2 @ UCSB E-Phi Runs)
    • Issue: Epi will arrive > 3 months -> test process follower with OPSIS run?


Issues brought up in meetings

13/01/2012

  • Sudha/Yongbo.: should we undercut to define the current channel?

- (Martijn) high risk
- REFERENCE EPI: centered QW, similar to past epi + top etch-stop layer + InGaAsP contact helper(?)
- HIGH RISK EPI: e-block layers, GRINSCH

  • Jon P.: Resist difficult to remove after Si-doping implants

- can remove with long strip, pirhana (hot)
- long-term: move to thin SiO2 underlayer (implant through this) and remove with BHF

  • Jared H.: edge bead (may not be an issue, esp. for 4" wafer processing - use stayout of 5-10mm)

- for small samples, can surround with additional chips during spin

06/01/2012

  • Jon P.: Resist nonuniformity for multiple-die exposure -> >= 1-cm stay-out area?
  • Jock: Grating module works for etch depths < 120 nm
  • Bandgap issue: PL peak is not equal to lasing wavelength, and lasing wavelength is not equal to SOA gain maximum
    • First have nice gain spectrum before we discuss further